Recommendations | Priority | Response and Planned Actions | Responsibilities (position title responsible for the action) |
Timelines |
---|---|---|---|---|
Ensure that a vehicle logbook is used to record usage on a daily basis, and a fleet management information system is in place to track maintenance, operating and repair costs related to fleet management. | Medium |
Response: We agree with the recommendation. Planned Actions: The audit found deficiencies in the fleet management records for the three cars owned and maintained by the department. It is noted that the total annual expenditures on these cars in 2013-14 was $3,265. Given that there are only three cars, the management response in this area is straightforward:
|
Executive Director, Finance & Corporate Management |
Complete |
Ensure that proper documentation is retained on file for acquisition cards to substantiate their issuance, approval, modification and conditions of use. | High |
Response: We agree with the recommendation. Planned Actions: At the time of the audit responsibility for acquisition cards was dispersed among the regions which could have led to a lack of consistency in documentation being retained regarding the issuance, approval, modification and condition of use of acquisition cards. Subsequently, in 2013-14, WD completed the centralization of the procurement function and provided training to all acquisition cardholders as regions were brought onto the new system from December 2012 to June 2013. These measures are expected to improve compliance in this area. The Manager of Corporate Administration will conduct a review of cardholder administration files to be completed by the end of October 2014 to ensure the following are on each file:
WD's ongoing training will be strengthened to address the recommendation and remind staff of requirements. |
Executive Director, Finance & Corporate Management |
Complete |
Ensure that:
|
High |
Response: We agree with the recommendation. Planned Actions: This is the area of greatest focus in terms of effecting substantial improvement of management practice. While management is satisfied with the administration and disclosure of large contracts, there are deficiencies noted, particularly in the administration of small contracts, which will be addressed. Even in instances where the record shows that competitive processes have been used for small transactions, WD recognizes that it is important to have on file all additional supporting documentation regarding the process and criteria used. In September 2013 WD completed the centralization of procurement and contract management which has a significant impact on the administration of small contract administration. This centralization is enhancing the scrutiny of contracting administration to ensure consistent policy compliance. New procedures have been developed for the centralized procurement unit to ensure appropriate procurement vehicles are chosen:
In addition, the Manager of Corporate Administration will develop a checklist for staff to better assess that all required documents are on file. In addition the Manager of Corporate Administration will work with regions and the OCG to identify areas where policy interpretation is required, particularly the requirement to use a contracting vehicle rather than an acquisition card for small dollar value purchases. It is recognized that, while the structure and system has recently been put in place to meet policy compliance objectives, structure and system alone will not succeed without adequate resourcing and training of staff. Accordingly, training was provided to all staff involved in the procurement and contracting function in May and June 2013. A Help Desk has been established to assist staff working in all branches of WD to identify the appropriate procurement vehicle and track procurements. The Manager, Managerial Accountability and Planning will sample contracting files in January 2015 to ensure the new system is working and training has been effective in addressing compliance. Furthermore, WD's internal monitoring plan will be adjusted to incorporate a greater focus on procurement to provide management with information on whether deficiencies have been addressed in a sustained way. Finally, with respect to contracts having a value of over $10,000, WD uses a contract review committee to review procurements including ensuring pro-active disclosure of these contracts. The one contract identified in the audit as not having been pro-actively disclosed related to an annual subscription (a membership in an organization with substantial benefits to the department) which was renewed, without being reviewed by the committee nor proactively disclosed. This contract will be disclosed for the next reporting period (by October 31, 2014) to ensure transparency. Further, WD management is now aware that subscriptions are subject to the requirements of the contracting policy. |
Executive Director, Finance & Corporate Management |
Complete |
Ensure that:
|
Medium |
Response: We agree with the recommendation Planned Actions: WD management will address many of the recommendations with the introduction of new travel management systems. Perhaps the most significant is WD's introduction of the PWGSC Shared Travel System (STS) in April 2014. The STS system includes the following features:
|
Executive Director, Finance & Corporate Management |
Complete |
Ensure that documentation that supports hospitality events is retained on file. | High | Response: We agree with the recommendation. Planned Actions: Hospitality expenditures have been reduced significantly in the department. In 2013-14 total hospitality expenditures were $6,240 which is an 80 percent decrease over the past year. The recently-established centralized accounting unit is tasked with checking hospitality-related documentation to ensure the recommendation is addressed and will provide periodic reminders and training for staff on a targeted basis. |
Executive Director, Finance & Corporate Management |
Complete |
Ensure that designated senior-level Government of Canada hospitality expenses are appropriately coded for purposes of proactive disclosure on WD's website. | High | Response: We agree with the recommendation. Planned Actions: The audit identified one $37 transaction that was coded incorrectly and as a result was not identified for proactive disclosure. The transaction was disclosed on September 30, 2014. Monitoring will review for coding errors and if identified, will recommend the necessary steps to correct. |
Executive Director, Finance & Corporate Management |
Complete |
Ensure that performance agreements and appraisals are signed and dated by concerned parties. | Medium | Response: We agree with the recommendation. Planned Actions: WD has a strong performance management system including annual commitments, related learning plans, and mid-year and year-end evaluations. As noted by the audit, however, documents are not always signed and dated and one form did not contain signature blocks to document the discussion and acknowledgement of performance objectives at the beginning of the year. Beginning 2013-14 a government wide Performance Management System was introduced which will provide exception reporting and ensure that all performance agreements, learning plans and appraisals are signed and dated by all concerned parties. This is currently in place for all non-EX employees and is expected to be in place for EX employees for 2015-16. For the 2014-15 year, completed EX Performance Agreements, learning plans and appraisals will be provided to the Chief of Compensation Services who will ensure all agreements are signed and dated as part of the mid-year review process currently underway. |
Executive Director, Finance & Corporate Management |
Complete |
Ensure that employees' departure forms are appropriately completed by applicable authorities. | Medium | Response: We agree with the recommendation Planned Actions: Departure forms involve a number of functions including Human Resources and Security. To ensure consistency, the Director of Human Resources will assume responsibility for coordinating departures. In addition, delegated managers will be reminded of their role in the process and training will be provided. A review of departure forms will be done by March 2015 and WD's internal control monitoring plan will be adjusted to incorporate this review. |
Executive Director, Finance & Corporate Management |
Complete |
Ensure that supporting documentation is on file and in accordance with the terms and conditions of the funding agreement. | High | Response: We agree with the recommendation. Planned Actions: Although WD management is satisfied with the overall management of grants and contributions as evidenced by the over 90% compliance results in this audit, there are areas of the administration of grants and contributions that can be reviewed and strengthened as indicated below. WD will continue to administer contribution agreements using a risk based approach as required by the Policy on Transfer Payments, consistent with the Blue Ribbon Panel on the Reform of Grants and Contributions. WD is working with other Regional Development Agencies on a common grants and contribution management system that will also support improved documentation. We will address these issues as part of our ongoing annual training of officers to ensure compliance is further strengthened. Project Lifecycle training for the current fiscal year is planned for January 2015. In addition, WD will review its Control Based Monitoring Framework and provide additional training to officers and managers. |
ADM Policy and Strategic Direction | Complete |
Ensure that expenditure initiation is properly documented and performed by an individual who has the appropriate delegated authority before expenses are incurred. | High | Response: We agree with the recommendation. Planned Actions: WD will strengthen its ongoing training and communicate to managers with financial signing authority on the requirements for expenditure initiation. This will include an emphasis to sign and date documents to ensure the audit findings identified are addressed with staff. Emphasis will be placed on acquisition card and petty cash transactions where most of the findings occurred as expected given the nature of those transactions. For the 2014-15 fiscal year, WD will monitor a sizable sample of operational expenditures. Based on the results of this review additional targeted measures will be implemented as required. Staff in the centralized accounting unit will also review all financial transactions to ensure the requirements of Section 32 are being met and send reminders to staff where deficiencies are noted. WD will review and update its internal controls monitoring plan to ensure adequate coverage on expenditure initiation. |
Executive Director, Finance & Corporate Management |
Complete |
Ensure that account verification is done by someone who has the appropriate delegated authority, is supported by complete documentation, and is done on a timely basis. | High | Response: We agree with the recommendation. Planned Actions: WD will strengthen its ongoing training and communicate to managers with financial signing authority on the requirements for account verification. This will include an emphasis on the requirement to date all signatures and attach all supporting documents received, such as packing slips, in addition to invoices to the file as these were common errors throughout the audit sample. For the 2014-15 fiscal year, WD will monitor of sample of operational expenditures. Based on the results of this review additional targeted measures will be implemented as required. Staff in the centralized accounting unit will also review all financial transactions to ensure the requirements of Section 34 are being met and send reminders to staff where deficiencies are noted. WD will also review its risk based internal control monitoring plan by November 30 to ensure appropriate coverage of account verification. |
Executive Director, Finance & Corporate Management |
Complete |